Downtown Bethesda's Capital Crescent Trail Detour Is the Trail Now

Montgomery County is building the street-level link between Ourisman Plaza and Elm Street Park as if it will last for years. The county's tunnel under Wisconsin Avenue has a $82.545 million line in the FY27 capital budget, and that same budget puts bid preparation, utility relocation and construction more than six years out. In the meantime, the county is building a 10-foot shared-use path along 47th Street, and Montgomery Parks is rebuilding Elm Street Park around the trail crossing.

So the street route through downtown is the Capital Crescent Trail for years to come, and October 2026 is when it starts to look the part.

Why the tunnel lost to the street

The decision is on the public record. Montgomery Parks' project page for Elm Street Park says the Purple Line required moving the trail, and two options were studied: a tunnel beneath Wisconsin Avenue and a surface route through Elm Street Park. In October 2021, the Montgomery County Planning Board approved both. Then, according to the parks department, "funding for the tunnel option was delayed beyond the current funding cycle," and MCDOT went ahead with the surface route through and alongside the park.

The tunnel is still planned. MCDOT describes it as a passage of about 1,000 feet starting at 7272 Wisconsin Avenue near Civic Green, running under Wisconsin Avenue and Elm Street, and coming out at Elm Street Park. The FY27 budget sheet lists it at the final-design stage. Final design with construction more than six years away means a set of drawings waiting for money. The route you can walk today is the one getting built out.

The route as it stands this October

MCDOT calls the street-level connection the Capital Crescent Surface Trail. Heading east from the existing trailhead, it runs like this:

  1. Ourisman Plaza to Bethesda Avenue. The off-road trail ends at the plaza, and the surface route picks up on Bethesda Avenue.
  2. Across Wisconsin Avenue. The route crosses at street level and ties into the Bethesda Avenue and Wisconsin Avenue bike-lane network.
  3. Willow Lane to 47th Street. Phase 2 adds the 10-foot shared-use path on 47th Street that connects Willow Lane to the Elm Street Park promenade.
  4. Into Elm Street Park. The promenade at 4600 Elm Street is the handoff point toward the old Georgetown Branch alignment, where the trail is being rebuilt next to the Purple Line.

On the status of step three: Montgomery Parks said on September 16 that the 47th Street segment was about 90% complete and expected to finish in October 2026. MCDOT's project page has photos dated August 6, 2026 showing finished sections at 47th and Elm and at Willow and 47th. As of October 11, neither agency has said the full path is open. Expect fencing and on-site signs until one of them does.

On foot, there is a second, separate detour to know about. Purple Line construction has closed pedestrian access between Wisconsin Avenue and Elm Street. The posted workaround uses the Wisconsin Avenue crossings at Elm Street and Waverly Street, goes west on Hampden Lane to Woodmont Avenue, and then onto Elm Street. That loop is for people walking around the station work zone. It is not the bike route, and the two can get confused at the Elm Street end.

Three timelines, three different scales

Three separate projects meet on this stretch, and each runs on its own clock.

Project What it covers Latest stated timing Source date
47th Street path, Surface Trail Phase 2 Willow Lane to Elm Street Park promenade October 2026, at about 90% complete Sept. 16, 2026
Main trail along the Purple Line Elm Street to Connecticut Avenue leg By spring 2027, with the trail 74% complete Oct. 5, 2026
Wisconsin Avenue tunnel About 1,000 feet, 7272 Wisconsin Ave to Elm Street Park Construction beyond six years FY27 budget

The middle row comes from a Montgomery County Council Transportation and Environment Committee briefing on October 5. WTOP reported that the Capital Crescent Trail was 74% complete and that the Elm Street to Connecticut Avenue leg is expected to open by spring 2027. The county's own capital project page for the trail gives the same spring 2027 target for main-trail construction along the Purple Line alignment. The Coalition for the Capital Crescent Trail's page still mentions a May 2024 forecast of a spring 2026 reopening, which predates these newer targets.

For now, the Purple Line project says crews are still building the line and the trail along the former Georgetown Branch Trail between Elm Street Park and Rock Creek Park, with work possible from 7 a.m. to 7 p.m. on weekdays and weekends through fall 2026.

The light rail is on its own schedule. At the same committee meeting, MTA's Ray Biggs told Chair Evan Glass that "the contractual date does remain December 30, 2027." When Glass asked about an April 2028 date, Biggs said the final date depends on safety testing, calling the process "dynamic," according to WTOP. WTOP put overall Purple Line construction at 92% complete.

The order of these dates matters for anyone on the trail. The walking and cycling link east of Elm Street is scheduled to reopen months before the trains run. Light-rail vehicles are already being tested between the Lyttonsville Operations and Maintenance Facility and Bethesda Station. Most of that testing happens between 7 a.m. and 7 p.m., but the project says vehicles could move at any time, day or night, and asks the public to stay outside the work zone.

Elm Street Park is being rebuilt around the crossing

The park at the end of the route is changing too. Elm Street Park covers two acres and sits inside Town of Chevy Chase limits, but Montgomery Parks maintains it. Phase 3 started in September 2026 and covers the larger renovation at the park's north end.

The design came out of public feedback collected in fall 2024. Priorities included inclusive play, better lighting and seating, protecting the trees in the southern part of the park, and "enhanced safety at the trail intersection." The plan includes:

  • An eastern playground for ages 2 to 12 with an enclosed harness swing, a low-floor cone spinner and a treehouse with a 4-foot slide
  • A middle play area for ages 5 to 12 with climbing towers of 8 and 15 feet, two slides and a rope tunnel
  • A fitness zone for ages 13 and up, including the balance-focused "Ocean Ring"
  • Flat, cork-based poured-in-place surfacing under both playgrounds

The bigger addition is still on paper. Bethesda Market Park would turn two surface parking lots next to the historic Bethesda Farm Women's Market into a park built over new underground parking. Combined with Elm Street Park, that would make about four acres of urban park space downtown. The project is a public-private partnership with Wisconsin Columbia Venture LLC, the owners of the Bethesda Market project co-developed by Bernstein Development Corporation and EYA Multifamily. As of the parks department's August 18 update, it is in preliminary planning, and a Preliminary Plan and Site Plan still need Planning Board approval. Montgomery Parks says the Elm Street Park playground equipment was chosen on purpose to differ from what is planned for Bethesda Market Park, so the two parks are designed to work together.

Where the route puts you

A street-level trail runs past storefronts, which the old tunnel never did. At the Ourisman Plaza end, Bethesda Bagels is at 4819 Bethesda Avenue, open daily, with online ordering. The Bethesda Row directory lists Quartermaine Coffee next door at 4817 Bethesda Avenue and Levain Bakery across the street at 4844, both with order-ahead links.

At the Elm Street Park end, the same directory lists Mamma Lucia at 4916 Elm Street, Jeni's Splendid Ice Creams at 4918 and Eat Sprout at 4926. Directories go out of date, so check hours before planning a ride around a stop.

When the Elm Street to Connecticut Avenue leg opens in spring 2027, those two clusters will be the downtown ends of a continuous trail heading east. The connection between them will still be Bethesda Avenue, a crossing of Wisconsin Avenue, Willow Lane and the 47th Street path, and the county's budget shows it staying that way well past the Purple Line's first day of service.

If being close to the trail and the future Bethesda Station is part of your next move, the Mike Aubrey Group can show you which blocks sit on the finished route and which are still behind construction fencing. Get in Touch.

Work With Us

Mike Aubrey Group of Berkshire Hathaway HomeServices PenFed Realty is a team of experienced, licensed real estate agents serving the Washington, DC, Montgomery County, MD metro area, and Northern Virginia. With a proven track record of getting results quickly and a direct line of communication at all times.

Follow Me on Instagram